Monday, 18 February 2013

Grid Lines!

The suspended ceiling grids are currently being installed and the permanent lighting is now installed, heating is commissioned and the lifts are now functional.
 
 

Wednesday, 6 February 2013

Retaining Wall Four

This week, works have commenced on the final retaining wall which when completed will allow for the rest of the car park to be completed and further works to progress. Once the car park is completed, the site cabins will be relocated from their current position which will then allow the ground workers to continue with their works in accordance with the construction programme.