Monday, 24 September 2012

Car Parking...

We have requested all our contractors be courteous when parking outside the site.  We have arranged for road cones to be placed, and have implemented a 'No Parking Zone' on one side of the road to enable traffic to pass un-impeded.
 
We have also negotiated an off site parking facility in an attempt to facilitate the ever increasing numbers of workers on site.
 

Progress on Woodland Court...

We have made some great progress over the past three weeks, and have commenced plastering in areas 4 and 3.
 
The sprinklers, mechanical and electrical are all progressing well, we have no more than 3 weeks' brickwork left on areas A, B and C, making way for progressive scaffold stripping by the end of October.
 
 

Introducing...

The wates team at Woodland Court welcomed the arrival of a new Site Manager - Paul Stogdale. Paul will assist the team on site to deliver the project on time and within budget, keeping a close eye on the quality and workmanship of the sub-contractors to ensure that the project is delivered to highest standard.

Friday, 14 September 2012

Let there be light

Works to the atrium are progressing in line with programme, with plastering now commencing in this area.
 
PRP Architects have designed the Atrium area to provide natural lighting though all three floors.
 
 
 

Wednesday, 12 September 2012

Right First Time

Kirklees Production Managers met earlier this week to ensure all properties constructed on the Excellent Homes for Living scheme are constructed to the same high quality standard throughout.
The meeting was chaired and facilitated by Martin Thomas, and attended by all production staff employed on the Kirklees project.
Many thanks to the two Andrews at Hare Park who hosted the event.

Monday, 10 September 2012

Coming to an End

By the end of this week all works to the timber frame will be completed. The men have worked through all kinds of weather to get the building completed in order for the follow on trades to commence the internal work by the contractual deadline.
Once the roof trusses are completed the roofing contractor will then be able to tile the entire roof which will make the building watertight.
 

Friday, 7 September 2012

Treesey Does It

The site team here at Woodland Court have agreed with Palmers, who have been selected as the preferred contractor to landscape the grounds, which trees will be planted around the site. Darran Morrison, Project Manager for Woodland Court said ' it is essential that the new trees match the existing sycamore and cherry trees so it looks like the new trees have been here for a long time. Planting season for trees and shrubs is normally during the month of October.